Project for the delivery of a batch of equipment (38 seats, 725 tons) from the raid of the port of New Amsterdam, Guyana to the destination station Kiya-Shaltyr, Russia
During the implementation of the project, the following were done:
- Development of a cargo plan taking into account transportation as Part cargo
- Approach of the vessel to the agreed point for the organization of raid transshipment
- Raid loading using a pair of ship cranes according to the barge-ship option, organization of cargo fastening by the ship’s crew
- Sea freight on FIOS New Amsterdam — St.Petersburg
- Cargo unloading, unloading by port crane to the terminal berth of Petrolesport
- Assistance in the dismantling of equipment for subsequent transportation by rail
- Transportation of goods by rail to the destination station Kiya-Shaltyr